Metro Offers Update on Rail-to-River Bike/Ped Path Design; Project to Break Ground Mid-2018

From LA.Streetsblog.org

 

On June 29, Metro held a public update on the Rail-to-River bike and pedestrian path project slated for the Slauson corridor in South L.A.

The update was to showcase the design progress on Segment A (in green, above) thus far, get feedback on the proposed design, and advise the community of next steps.

For those unfamiliar with the project, the Rail-t0-River project is an Active Transportation Corridor planned for the Metro-owned rail right-of-way (ROW) along Slauson Avenue in South Los Angeles. The 6.4 mile stretch of Segment A was planned to facilitate transit users’ movement between the Crenshaw, Silver, Blue, and local bus Lines, while Segment B (in pink) would connect South L.A. with the Southeast Cities and, eventually, the L.A. River, expanding the regional bicycle network.

Because Metro must negotiate with Union Pacific to access the ROW along Randolph Street (the route chosen for Segment B) and work out plans with the cities the route will pass through, planning for Segment A has moved at a much quicker pace. Metro expects to see the preliminary (30 percent) design completed shortly and to hire a design/build construction contractor to finish the plans and break ground by mid-2018.

The project would be completed in late 2019, around the time that the Crenshaw/LAX Line would be opening.

 